Skip to main content
logo
  • Investment Strategies

      Investment Options

      • Alternatives
      • Beta Strategies
      • Equities
      • Fixed Income
      • Global Liquidity
      • Multi-Asset Solutions

      Capabilities & Solutions

      • ETFs
      • Pension investment solutions
      • Global Insurance Solutions
      • Outsourced CIO
      • The power of active
      • Sustainable Investing
      • Investing in China
    • Insights

        Market Insights

        • Market Insights Overview
        • Eye on the Market
        • Guide to the Markets
        • Guide to Alternatives
        • Mid-Year Investment Outlook 2026
        • Guide to Investing in Asia
        • Why Alternatives?

        Portfolio Insights

        • Portfolio Insights Overview
        • Alternatives
        • Asset Class Views
        • Currency
        • Equity
        • ETF Perspectives
        • Fixed Income
        • Sustainable Investing Insights
        • Strategic Investment Advisory Group
      • Resources
          • Center for Investment Excellence Podcasts
          • Library
          • Webcasts
          • Morgan Institutional
          • Investment Academy
        • About us

            About us

            Backed by $4.6T in assets, we harness our active edge to deliver timely ideas and actionable insights that empower investors to achieve what matters most.

            • Our Leadership Team
          • Contact Us
          • Institutional Investors
            • LIQUIDITY INVESTORS
          You are about to leave the site Close
          J.P. Morgan Asset Management’s website and/or mobile terms, privacy and security policies don't apply to the site or app you're about to visit. Please review its terms, privacy and security policies to see how they apply to you. J.P. Morgan Asset Management isn’t responsible for (and doesn't provide) any products, services or content at this third-party site or app, except for products and services that explicitly carry the J.P. Morgan Asset Management name.
          CONTINUE Go Back
          On the Minds of Investors

          Will the data center backlash slow the AI buildout?

          SA
          Stephanie Aliaga

          Global Market Strategist

          Published: 06/11/2026
          How much this ultimately affects investment remains uncertain, given the economic incentives for states and localities to accommodate development.

          The AI buildout was on the ballot this year, and it lost. Democrats won governorships in major data center markets, like Texas and Ohio, after campaigning for moratoriums or tougher development requirements. Voters in communities across the country also backed restrictions on new projects.1

          Building out AI infrastructure was already a massive undertaking, with significant hurdles around power, permitting and financing. Growing political resistance adds to the difficulty, potentially bringing longer negotiations, higher costs and further delays. But how much this ultimately affects investment remains uncertain, given the economic incentives for states and localities to accommodate development.

          More bark than bite, so far

          Opposition to data centers had been building well before the midterms, reflecting bipartisan concerns about electricity bills, grid reliability and water consumption. Wood Mackenzie counts more than 400 state and local moratorium actions since January, against just 45 across all of 2023–2025.

          Yet many restrictions are temporary, and statewide moratoriums have struggled to advance: of 16 states considering legislation, only one has passed a bill through its legislature. Meanwhile, data center capacity under construction grew nearly 50% in the first half of 2026.2

          The potential economic benefits are also substantial. A U.S. Chamber of Commerce study estimates that a mid-sized 50 MW data center generates nearly $700 million in annual state GDP and supports more than 5,200 jobs per year during construction.3

          Finding the right model for states and developers

          Newly elected officials will likely take a firmer stance to deliver on campaign promises. Over time, however, local governments must weigh constituent concerns against the investment, tax revenues and jobs data centers can bring.

          States are still determining what a fair deal with developers should look like. Utility regulators are seeking commitments to ensure households don't shoulder incremental grid costs. Developers, meanwhile, are offering more substantial community benefits: Amazon and Google have each announced roughly $1 billion in community investment initiatives. Many are also exploring dedicated power generation to reduce reliance on constrained grids.

          These arrangements could help secure community support, but also raise costs and prolong negotiations. The evolution of public sentiment toward AI will influence how welcoming politicians can afford to be.

          What does this mean for the AI trade?

          Political resistance could reshape where capacity gets built, which projects move forward and which developers are best positioned to deliver.

          • The buildout from 2028 onward is most exposed. Projects already under construction are generally less vulnerable to new restrictions. Future developments face greater uncertainty around permitting, power availability and financing, with delays and higher costs potentially pressuring returns.
          • A shakeout of speculative projects may be healthy. Wood Mackenzie estimates more than 430 GW of proposed U.S. data center capacity, but just 59% is under active development.4 Utilities are already weeding out speculative power requests, and higher hurdles could accelerate this process. This should favor well-capitalized hyperscalers and developers with stronger economics, while reducing the risk of speculative overbuilding.
          • Investment can move elsewhere. Extraordinary demand for compute should continue to fuel construction, potentially drawing investment toward more welcoming states or international markets. Developers will also likely pursue dedicated power generation, albeit at additional cost.

          Ultimately, AI adoption, monetization and access to capital will remain the primary drivers of investment beyond the midterms. But how developers and policymakers navigate growing infrastructure challenges will help determine whether the next phase of AI growth remains constrained by energy shortages, or enabled by energy abundance.

          1 According to Ballotpedia, voters favored restrictions in 40 of 41 local data center-related measures on November 3, either approving new restrictions or rejecting pro-development proposals.
          2 Cushman & Wakefield, Americas Data Center Update, H1 2026, September 14, 2026. Capacity under construction increased from 25.3 GW at year-end 2025 to 37.7 GW in June 2026.
          3 U.S. Chamber of Commerce, One Mid-Sized Data Center Can Generate Nearly $700 Million in Economic Output and Support 5,200 Jobs, October 15, 2026. Estimates based on a modeled 50 MW data center and include direct, indirect and induced effects across the state economy.
          4 Wood Mackenzie, U.S. Data Center Pipeline, Q3 2026. Active development covers projects progressing through siting, permitting and construction. 
          b71d5d2e-d889-11f1-a5de-21e9d6ca1823

          About the Author

          Latest from the Author

          What does a Democratic Congress mean for markets?
          November 04, 2026 Stephanie Aliaga
          Could rising AI debt derail the investment boom?
          October 23, 2026 Stephanie Aliaga
          Are companies benefiting from AI adoption?
          October 16, 2026 Stephanie Aliaga
          Why are AI labs raising red flags around AI safety?
          September 16, 2026 Stephanie Aliaga
          How is the U.S.-China AI race evolving?
          September 09, 2026 Stephanie Aliaga
          • Artificial Intelligence
          • Infrastructure
          • U.S. Elections
          J.P. Morgan Asset Management

          • About us
          • Investment stewardship
          • Privacy policy
          • Cookie policy
          • Sitemap
          J.P. Morgan

          • J.P. Morgan
          • JPMorgan Chase
          • Chase

          READ IMPORTANT LEGAL INFORMATION. CLICK HERE >

          The value of investments may go down as well as up and investors may not get back the full amount invested.

          Copyright 2026 JPMorgan Chase & Co. All rights reserved.