Skip to main content
logo
  • Insights

      Liquidity Insights

      • Liquidity Insights Overview
      • Global Liquidity Investment Outlook
      • Tokenization
      • Case Studies
      • Partnership with fintechs
      • ESG Resources for Liquidity Investors
      • Leveraging the Power of Cash Segmentation
      • Cash Investment Policy Statement

      Market Insights

      • Market Insights Overview
      • Eye on the Market
      • Guide to the Markets

      Portfolio Insights

      • Portfolio Insights Overview
      • Currency
      • Fixed Income
      • Strategic Investment Advisory Group
    • Resources
        • MORGAN MONEY
        • Global Liquidity Investment Academy
      • About us

          About us

          We harness our active edge to deliver timely ideas and actionable insights that empower investors to achieve what matters most.

          • Our Leadership Team
          • Diversity, Opportunity & Inclusion
        • Contact us
        • LIQUIDITY INVESTORS
          • INSTITUTIONAL INVESTORS
        You are about to leave the site Close
        J.P. Morgan Asset Management’s website and/or mobile terms, privacy and security policies don't apply to the site or app you're about to visit. Please review its terms, privacy and security policies to see how they apply to you. J.P. Morgan Asset Management isn’t responsible for (and doesn't provide) any products, services or content at this third-party site or app, except for products and services that explicitly carry the J.P. Morgan Asset Management name.
        CONTINUE Go Back
        On the Minds of Investors

        Will the data center backlash slow the AI buildout?

        SA
        Stephanie Aliaga

        Global Market Strategist

        Published: 06/11/2026
        How much this ultimately affects investment remains uncertain, given the economic incentives for states and localities to accommodate development.

        The AI buildout was on the ballot this year, and it lost. Democrats won governorships in major data center markets, like Texas and Ohio, after campaigning for moratoriums or tougher development requirements. Voters in communities across the country also backed restrictions on new projects.1

        Building out AI infrastructure was already a massive undertaking, with significant hurdles around power, permitting and financing. Growing political resistance adds to the difficulty, potentially bringing longer negotiations, higher costs and further delays. But how much this ultimately affects investment remains uncertain, given the economic incentives for states and localities to accommodate development.

        More bark than bite, so far

        Opposition to data centers had been building well before the midterms, reflecting bipartisan concerns about electricity bills, grid reliability and water consumption. Wood Mackenzie counts more than 400 state and local moratorium actions since January, against just 45 across all of 2023–2025.

        Yet many restrictions are temporary, and statewide moratoriums have struggled to advance: of 16 states considering legislation, only one has passed a bill through its legislature. Meanwhile, data center capacity under construction grew nearly 50% in the first half of 2026.2

        The potential economic benefits are also substantial. A U.S. Chamber of Commerce study estimates that a mid-sized 50 MW data center generates nearly $700 million in annual state GDP and supports more than 5,200 jobs per year during construction.3

        Finding the right model for states and developers

        Newly elected officials will likely take a firmer stance to deliver on campaign promises. Over time, however, local governments must weigh constituent concerns against the investment, tax revenues and jobs data centers can bring.

        States are still determining what a fair deal with developers should look like. Utility regulators are seeking commitments to ensure households don't shoulder incremental grid costs. Developers, meanwhile, are offering more substantial community benefits: Amazon and Google have each announced roughly $1 billion in community investment initiatives. Many are also exploring dedicated power generation to reduce reliance on constrained grids.

        These arrangements could help secure community support, but also raise costs and prolong negotiations. The evolution of public sentiment toward AI will influence how welcoming politicians can afford to be.

        What does this mean for the AI trade?

        Political resistance could reshape where capacity gets built, which projects move forward and which developers are best positioned to deliver.

        • The buildout from 2028 onward is most exposed. Projects already under construction are generally less vulnerable to new restrictions. Future developments face greater uncertainty around permitting, power availability and financing, with delays and higher costs potentially pressuring returns.
        • A shakeout of speculative projects may be healthy. Wood Mackenzie estimates more than 430 GW of proposed U.S. data center capacity, but just 59% is under active development.4 Utilities are already weeding out speculative power requests, and higher hurdles could accelerate this process. This should favor well-capitalized hyperscalers and developers with stronger economics, while reducing the risk of speculative overbuilding.
        • Investment can move elsewhere. Extraordinary demand for compute should continue to fuel construction, potentially drawing investment toward more welcoming states or international markets. Developers will also likely pursue dedicated power generation, albeit at additional cost.

        Ultimately, AI adoption, monetization and access to capital will remain the primary drivers of investment beyond the midterms. But how developers and policymakers navigate growing infrastructure challenges will help determine whether the next phase of AI growth remains constrained by energy shortages, or enabled by energy abundance.

        1 According to Ballotpedia, voters favored restrictions in 40 of 41 local data center-related measures on November 3, either approving new restrictions or rejecting pro-development proposals.
        2 Cushman & Wakefield, Americas Data Center Update, H1 2026, September 14, 2026. Capacity under construction increased from 25.3 GW at year-end 2025 to 37.7 GW in June 2026.
        3 U.S. Chamber of Commerce, One Mid-Sized Data Center Can Generate Nearly $700 Million in Economic Output and Support 5,200 Jobs, October 15, 2026. Estimates based on a modeled 50 MW data center and include direct, indirect and induced effects across the state economy.
        4 Wood Mackenzie, U.S. Data Center Pipeline, Q3 2026. Active development covers projects progressing through siting, permitting and construction. 
        b71d5d2e-d889-11f1-a5de-21e9d6ca1823

        About the Author

        Latest from the Author

        What does a Democratic Congress mean for markets?
        November 04, 2026 Stephanie Aliaga
        Could rising AI debt derail the investment boom?
        October 23, 2026 Stephanie Aliaga
        Are companies benefiting from AI adoption?
        October 16, 2026 Stephanie Aliaga
        Why are AI labs raising red flags around AI safety?
        September 16, 2026 Stephanie Aliaga
        How is the U.S.-China AI race evolving?
        September 09, 2026 Stephanie Aliaga
        • Artificial Intelligence
        • Infrastructure
        • U.S. Elections
        J.P. Morgan Asset Management

        • Investment stewardship
        • About us
        • Contact us
        • Privacy policy
        • Cookie policy
        • Sitemap
        J.P. Morgan

        • J.P. Morgan
        • JPMorgan Chase
        • Chase

        READ IMPORTANT LEGAL INFORMATION. CLICK HERE >

        The value of investments may go down as well as up and investors may not get back the full amount invested.

        Copyright 2026 JPMorgan Chase & Co. All rights reserved.